top of page
lake and clouds distance shot.jpg

A View from the Lake by Tom Schroeder - President, Beaver Dam Lake Management District, September 18, 2024

On Monday, Sept. 16, 2024 the restoration/dredging of Library Lake began with Haas Inc. –

Thorp, WI. mobilizing to begin the process of installing sheet piling to block off of the channel

under the Grove Street bridge between Library Lake and Rabbit Bay. Following the installation

of the sheet piling, pumps will start the process of lowering the Lake by 4 to 5 feet by Oct. 1st per

the WDNR permit requirements. The Lake will remain lowered until after the dredging is

completed hopefully by mid. Jan. through Feb. 2025. With the forecasted influence of the La

Nina weather event causing lower than normal winter temperatures, the cattail and sediment will

hopefully be sufficiently frozen to allow the heavy backhoes and trucks to traverse the lake bed.

Over 1000 truckloads of material will be removed.


Because the WDNR would not permit the dredging along the north shore to take place closer

than 30 ft. from the shoreline, the BDLMD is working to obtain approval for the resident riparian

owners along Grove Street to opt for removing sediment along their respective shoreline for

docks and mooring of watercraft. This would be done concurrent with the dredging along the

north shore of Library Lake and would be at the owners expense.


The fund raising for Restoring Library Lake continues and any funds raised beyond the dredging

costs will be used for additional enhancements along the Library Lake Shoreline and the SE

storm water park. Thanks to those that have already donated and to all others, please consider

donating. A “Venmo” account is available and a savings account specifically for the donations to

the project is in place at Cumberland Federal Bank. Donations to the Library Lake Restoration

fund can be mailed to the BDLMD at P.O. Box 232, Cumberland, WI. 54829 or dropped off at

Cumberland Federal Bank. Anyone wishing to donate stock to take advantage of tax

opportunities please contact your financial advisor or Matt Gores at Edward Jones. Go to

beaverdamlake.org for more details on the dredging project and how to donate.


The stop logs and side boards at the Dam were lowered on July 30th and Aug. 11th respectively,

when the lake was still several inches above normal. However, with the lack of sufficient rain

and the high evaporation rate, the lake level has continued to decline to about 4 inches below

normal. Hopefully we will get some substantial rain soon.


Be sure to watch Library Lake level go down. It is soon going to look a lot different!




32 views0 comments

Comments


bottom of page